On 2 November 2026, Ecologia Environmental Solutions, RemedX, RSK Raw, RSK Response and RSK IWS came together as Penta Environmental. The new organisation combines specialist expertise in environmental response, remediation and water treatment, giving clients across the UK access to broader capabilities and greater capacity.

Project overview

RSK Response provided an environmental incident response following a hydraulic oil release from components within the nacelle of a turbine on a wind farm. About 50 to 100 litres of hydraulic oil was released, which travelled down the turbine tower and impacted the surrounding hardstanding and made ground.

Following repair of the initial leak, a subsequent release occurred after the turbine was returned to service and was managed as part of the same response.

The solution

RSK Response attended on the day of the initial incident while the leak was ongoing. The client’s engineers had deployed oil-selective absorbents around the turbine base, and RSK Response installed additional absorbents around the turbine and hardstanding boundary to prevent migration into the surrounding soils. Following completion of repairs, RSK Response inspected the affected area and collected soil samples to inform the waste disposal route. When further leakage was subsequently reported, the client absorbents were replaced and additional oil-selective absorbents deployed to maintain containment.

Environmental assessments

The environmental assessment considered potential impacts to soil, vegetation, groundwater and surface water, using a source pathway receptor approach. Groundwater was treated as a sensitive receptor because of the underlying moderately productive bedrock aquifer. The nearest surface watercourse, Auchter Water, approximately 305 m from the turbine, was assessed and discounted as a significant pollutant linkage owing to its distance, local topography and ground conditions.

Excavation of the impacted made ground

Following completion of the turbine repairs and associated logistical arrangements, RSK Response coordinated excavation of the impacted made ground. About 4.7 tonnes of oil-impacted material was excavated and removed to a suitably licensed hazardous waste facility. Excavation continued until no further visual or olfactory evidence of hydrocarbon contamination was identified within the accessible made ground. Remaining absorbents were removed and residual surface contamination accessible from ground level was treated using degreaser.

Validation soil samples were collected following excavation and analysed for petroleum hydrocarbons. Although residual hydrocarbons were detected, the individual hydrocarbon fractions were below the adopted generic assessment criteria. The assessment concluded that the principal source of contamination had been removed, no significant pollutant linkages remained and no further environmental remediation was required.

Discover more projects

Surcharge monitoring of a waste landfill using wireless sensor network

Surcharge monitoring of a waste landfill using wireless sensor network

Site investigation, contamination assessment and remediation of a former chemical plant

Site investigation, contamination assessment and remediation of a former chemical plant

Fluid-filled cable leak: Site of special scientific interest

Fluid-filled cable leak: Site of special scientific interest

In situ thermal desorption in chalk aquifer

In situ thermal desorption in chalk aquifer

Wallasea Island Wild Coast Project

Wallasea Island Wild Coast Project

Pole-mounted transformer catastrophic failure, private residence

Pole-mounted transformer catastrophic failure, private residence

Heating oil leak, Kent

Heating oil leak, Kent

Secret Link