A two-phase in situ thermal remediation scheme was successfully implemented to reduce contamination of soils and an underlying aquifer.


Categories
Remediation

On 2 November 2026, Ecologia Environmental Solutions, RemedX, RSK Raw, RSK Response and RSK IWS came together as Penta Environmental. The new organisation combines specialist expertise in environmental response, remediation and water treatment, giving clients across the UK access to broader capabilities and greater capacity.

Project overview

Historical benzene and volatile organic compound (VOC) contamination associated with the former chemical facilities site processes had impacted the soils and underlying aquifer.

The client’s onsite pump and treat system had confined the resulting plume to within the site boundary over a period of 15 years of operations. While effective in reducing the overall plume spread, the source of contamination needed to be remediated to enable the client to plan to surrender its environmental permit and divest the site, as well as to reduce any future liabilities.

The solution

Acting as both consultant and contractor (or ‘smart contractor’) a two-phase in situ thermal remediation scheme was successfully implemented . The scheme was part of a wider strategy, which consisted of the installation of a dual phase extraction system (DPE) system to ensure hydraulic containment in combination with steam injection (SI) of the deep aquifer and in situ conductive thermal desorption (ISTD) of the capillary fringe and unsaturated soils in order to meet the client’s accelerated divestment programme.

The initial stage was the heating of the aquifer to a temperature above the boiling point of benzene (i.e., >80ºC) over a period of 30 weeks, while ensuring hydraulic control of the aquifer. This was followed by an ISTD of the unsaturated soils at the point of loss and within the capillary fringe. A target average temperature of >80ºC in the soil was achieved after 18 weeks of thermal treatment.

The VOCs were captured by the DPE system and treated via granular activated carbon (GAC) filtration. Extracted groundwater was treated using an oil/water separator followed by GAC filtration, prior to licensed disposal to the foul sewer.

Once the system achieved the target temperature, both the SI and ISTD were switched off, whereas the DPE system operated for 52 weeks until asymptotic removal of VOCs was achieved.

Lastly, a period of air sparging was completed to further volatilise any remaining benzene and provide oxygenation to enhance the residual degradation of VOCs.

The result

The combined SI and ISTD system recovered >1.3 tonnes of VOCs from the air and liquid phase. This mass was approximately twice as much as the initial mass estimation calculated using site investigation data during the installation of the system.

Groundwater concentration reached a peak concentration of >66 mg/L during treatment and evidence of free phase VOCs was also observed in the groundwater.

The system is currently undergoing rebound monitoring and average groundwater concentrations have reduced by >85% from initial concentrations.

Throughout the works, there was and significant engagement and liaison with the regulators, owing to the complexity and sensitivity of the site, which continues to ensure the system is operating efficiently.

Discover more projects

Surcharge monitoring of a waste landfill using wireless sensor network

Surcharge monitoring of a waste landfill using wireless sensor network

Site investigation, contamination assessment and remediation of a former chemical plant

Site investigation, contamination assessment and remediation of a former chemical plant

Fluid-filled cable leak: Site of special scientific interest

Fluid-filled cable leak: Site of special scientific interest

Wallasea Island Wild Coast Project

Wallasea Island Wild Coast Project

Pole-mounted transformer catastrophic failure, private residence

Pole-mounted transformer catastrophic failure, private residence

Hydraulic oil spill on wind farm

Hydraulic oil spill on wind farm

Heating oil leak, Kent

Heating oil leak, Kent

Secret Link