As materials management and contamination specialists for the project, we helped contribute to a new wetland nature reserve of reclaimed saltmarsh.


Categories
Geoenvironmental

On 2 November 2026, Ecologia Environmental Solutions, RemedX, RSK Raw, RSK Response and RSK IWS came together as Penta Environmental. The new organisation combines specialist expertise in environmental response, remediation and water treatment, giving clients across the UK access to broader capabilities and greater capacity.

Project overview

The Wallasea Island Wild Coast Project is a flagship site for the RSPB, who partnered with Crossrail to reuse excavated Crossrail construction spoil from across London, to create a new wetland nature reserve covering a total area of 677 hectares of reclaimed saltmarsh.

BAM Nuttall was appointed to implement these works, who in turn employed us as materials management and contamination specialists.

The solution

The Docklands Transfer Site was constructed by BAM Nuttall for the receipt of Crossrail spoil, comprising multiple waste streams with several hundred lorry deliveries per day. Specialist cargo ships were used to move 3 million tonnes of Crossrail spoil during the project.

In order to receive the spoil, BAM Nuttall constructed an unloading facility at Wallasea Island with a half-mile conveyor system to carry material on to the land, and earthworks plant to place in the permanent works.

In consultation with the Environment Agency, a bespoke risk-based environmental permit for waste recovery was adopted. The Wallasea Island Waste Acceptance Procedure (WAP) was subsequently produced to manage excavated Crossrail spoil, and the procedure was continually updated during the project by Crossrail, its advisers, BAM Nuttall and our project teams.

Compliance checking for heavy metals, hydrocarbons and chlorinated solvents using rapid measurement testing (RMT) techniques was undertaken in a temporary on-site laboratory at the Docklands Transfer Site. This provided a far larger data set than would have been possible with traditional laboratory testing approaches, which therefore provided a greater level of robustness and surety in relation to materials control, quality and verification. In total, over 12,500 samples were analysed.

All the results were continuously checked and assessed in order to identify any exceedances of the thresholds, reject unsuitable loads and monitor trends in the data and material.

As part of the WAP, each Crossrail site producing spoil for import to Wallasea Island was required to complete a waste information form. This form detailed the material and provided any supporting information that was reviewed for acceptance before the waste was transported to Wallasea Island. For example, it covered the approved use of additives in the tunnelling works and recognised that London Clay (and other natural soils) may contain elevated levels of naturally occurring elements. In relation to the latter, a hydrological risk assessment was undertaken to derive Crossrail-specific Waste Acceptance Criteria levels.

Aerial view of Wallasea Island
Wallasea Island green grass and dry land

The outcome

On completion of the works, BAM Nuttall successfully surrendered the environmental permit for Wallasea Island. This was achieved by demonstrating compliance with the permit’s requirements and by Ecologia preparing verification reports for Wallasea Island compliance testing and a separate consolidated report in relation to the RMT testing at The Docklands Transfer Site.

Discover more projects

Surcharge monitoring of a waste landfill using wireless sensor network

Surcharge monitoring of a waste landfill using wireless sensor network

Site investigation, contamination assessment and remediation of a former chemical plant

Site investigation, contamination assessment and remediation of a former chemical plant

Fluid-filled cable leak: Site of special scientific interest

Fluid-filled cable leak: Site of special scientific interest

In situ thermal desorption in chalk aquifer

In situ thermal desorption in chalk aquifer

Pole-mounted transformer catastrophic failure, private residence

Pole-mounted transformer catastrophic failure, private residence

Hydraulic oil spill on wind farm

Hydraulic oil spill on wind farm

Heating oil leak, Kent

Heating oil leak, Kent

Secret Link